Contractors Complete 123 km of 156 km Lagos-Ibadan Rail Project

Lagos State

The Minister of Transportation, Mr Rotimi Amaechi, said 123km of the 156 km stretch of the Lagos-Ibadan standard guage rail project has been completed.

Amaechi made the disclosure on Friday during his routine inspection of the project along Kila, Olodo, Ilugun corridor of the track in the outskirts of Ogun State.
He said the project had been completed up to Kila village, a settlement on the outskirts of Ogun towards Oyo State.

“We are already moving towards Ibadan, the track laying is now in Kila, a town on the outskirts of Ogun.
“In less than a month from now, we should be in Ibadan with the rate the work is going,” he said.

The Minister also said that he would inspect the Apapa port and its connection to the standard guage rail to address the challenges of traffic gridlock in the area.
“We will be visiting the ports tomorrow to address some of the issues we have there.
“It’s imperative that the Apapa ports must be connected to the standard guage rail to ensure proper movement of cargoes,” Amaechi said.

The News Agency of Nigeria (NAN) reports that the minister had during one of his inspection tours on April 8 blamed the China Civil Engineering Construction Corporation (CCECC) for the slow pace of work in the ongoing project.

According to him, the Federal Government plans to commence transportation of cargoes from the sea ports through the standard rail gauge by December.

Source: NAN

LEAVE A REPLY

Please enter your comment!
Please enter your name here