TCN Wheels Out 3,403Megawatts to DisCos

The Nigeria Electricity System Operator, SO, of the Transmission Company of Nigeria, TCN, on Wednesday, September 14, said it evacuated 3,403 Megawatts of electricity to the 11 Distribution Companies, DisCos, nationwide.

In its daily summary of power sector performance, the SO said that at 06:00hours on Wednesday, the generation companies (GenCos) produced 82,461.95MWH, which is equivalent of 3,435.91Mw from the gas and hydro power plants.

The Nigerian Electricity Supply Industry, NESI, however said the gas shortage culminated in the loss of 3,105Mw, adding that its gas constraint was 3,105Mw, while line constraint was 495.4Mw, and frequency constraint was 118.4MW.

It said there was no water management constraint, but pointed out that the power sector loss was equivalent of N1.785billion

It said : “On September 12 2016, average power sent out was 3403MWh/hour (down by 20MWh/h). The reported gas constraint was 3105MW. The reported line constraint was 495.4MW according to TCN. The reported high frequency constraint was 118.4 MW.”

NESI maintained that the water management constraint was 0MW and the power sector lost the estimated equivalent of N1.785billion on September 12 2016 due to constraints.