23 Oil Blocks Weren’t Operational – FG

Nigerian Oil Companies Risk Sanction

According to the Federal Government, 23 oil blocks operated by both multinational and local oil corporations that are under crude oil Production Sharing Contracts with the Nigerian National Petroleum Company Limited failed to produce crude or were inactive.

This was revealed in the newest Oil and Gas Industry Report for 2021 provided by the Nigeria Extractive Industries Transparency Initiative, a Federal Government organization. It reported that the blocks did not generate oil during the fiscal year under consideration.

A PSC is an agreement or contract in which the contracted oil firm agrees to fund activities to explore, develop, and produce petroleum inside a concession area, under an Oil Prospecting License, and for an agreed-upon number of years.

If the endeavor is successful, the corporation will be required to pay the government Petroleum Profit Tax, royalty, and additional bonuses/levies. The corporation has the right to recoup its expenditures in-kind through a process known as “Cost Oil.”

Through the NNPC’s arrangement of lifting crude oil and gas for tax, royalty, and share of profit oil (typically divided in a specified ratio), for sale and payment to designated accounts, the firm also pays PPT and royalty in-kind. The account might be a Federal Inland Revenue Service (tax) or DPR (now NUPRC) account (royalty), with earnings from the sale of profit oil going straight to the Federation Account. Because the corporation absorbs the expense of exploration, PSC relieves the government of financial load.

An analysis of the latest NEITI reportindicated that in 2021, 12 of the PSC oil blocks made production, while 17 blocks did not produce. The report showed that there were also six inactive blocks, bringing the total number of both inactive oil blocks and those that did not produce crude during the review period to 26.

Some of the PSC contractors that did not produce crude from selected blocks included Esso E&P, Nigerian Agip Exploration, Shell Nigeria Exploration and Production Company, Texaco Nigeria Outer Shelf Limited, Star Deep Water Petroleum Limited, Statoil Nigeria Limited.

Others included Newcross Petroleum Limited, Sahara Energy Exploration and Production Limited, Conoil Producing Limited, Continental Oil and Gas Limited, Enageed Resources Limited, Nig-Del United OIl Company Limited, Sterling Oil Exploration and Energy Production Company Limited, among others. The contractors managing the six inactive PSC blocks included GEC Petroleum Development Company Limited, Nigerian Agip Oil Company, Monipulo Limited, and Esso Exploration and Production Limited.

Commenting further on the development, NEITI said, “The following were the observations on production from PSC blocks In 2021: Only 12 (34 per cent) of the PSC blocks recorded production, while 23 other blocks, representing 66 per cent of total numbers of PSC blocks, did not produce.

“Total production from the PSCs, which was 242.96 million barrels, represents 42.92 per cent of total production of the 566.13 million barrels.”

On the implication of this, the agency said, “The PSC arrangements, which contributed highest to the total production volumes, operated only 34 per cent of the total allocated blocks.”

It recommended that there was the need for the Nigeria Upstream Petroleum Regulatory Commission, and NNPC Ltd to speedily review the technical, operational and other constraints limiting production from the idle PSC blocks with the view of optimising production from the PSC arrangements.

“Where these issues cannot be resolved, consider revocation of licenses and subsequent allocation to other interested parties,” the Federal Government agency stated.

NEITI, however, captured the responses from NNPCL as regards the development, as it stated that the national oil firm explained that “PSC blocks transit from exploration/appraisal phase to production overtime.”

It stated that the oil firm also noted that “some of the blocks are still at award status as some contractors may not have come forward for budget/work programmes due to various reasons from regulatory to business operations’ considerations.

“We (NNPCL) are hopeful that about two to three blocks will soon attain production status.”

The Federal Government partners indigenous and foreign oil firms to explore and produce Nigeria’s crude, due to the high technology required for these services, and PSC is one of such major partnerships.