Breach In Gas Supply Forces Six Power Plants To Halt Operations

Blackout Looms As TCN Hints At Power Supply Drop

A breach in the supply of gas to the facilities has resulted in suspension of operations of six power plants under the management of the Niger Delta Power Holding Company.

In a letter dated December 20, 2021, from the NDPHC to the Managing Director of the Nigerian Bulk Electricity Trading Plc the breach was reported by the Nigeria Gas Company, the gas supplier to the plants.

The letter titled, “Re: Notice of gas shortage from Nigeria Gas Company”, disclosed that five of the power plants were affected by the gas curtailment, while one was forced to shut down.

It read in part, “We (NDPHC) have been notified on December 18, 2021, by the Nigeria Gas Company, via an email (Annexure I) of a breach on their gas supply network as well as technical issues affecting gas suppliers on the western axis.

“These challenges have led the NGC to issue the notice of gas curtailment arising from the abysmal system pressure levels that must be managed to avoid collapse of the gas grid.”

It added, “According to the NGC, the Trans-Forcardos Pipeline was breached on December 17, 2021 and has impacted Seplat’s production and may affect other producers if not immediately repaired.

“Also, the NGC reported that the Nigeria Petroleum Development Company’s Ughelli East Plant is currently down, while Chevron Nigeria Limited had also lost a compressor because of technical issues.”

It stated that the combined impact of all these issues was a deferment, unavailability to off-takers, of about 250 million standard cubic feet of gas from the pipeline network.

On plants that were affected, the power firm said, “The NHPHC has five of its operational power plants viz, Olorunsogo, Omotosho, Sapele, Ihovbor and Geregu impacted by this gas curtailment, while Omotosho NIPP (National Integrated Power Project) has been forced to shut down.

“Geregu NIPP and Ihovbor NIPP are only receiving limited gas volumes thus leading to part load or low generation operation.”

The letter, however, noted that the management of the NDPHC was keeping track of the situation and was committed to making certain that the plants resume full operations immediately gas supply improves.